Bilmar completed a multidisciplinary Pre FEED study supporting the development of a proposed 1.4 GW behind the meter power generation facility serving a large scale data center development in West Texas. Engineering teams coordinated with ERCOT, transmission providers, and natural gas utilities to evaluate multiple substations, available utility capacity, and conceptual interconnection strategies. Bilmar also worked with leading power generation manufacturers to evaluate generation technologies, developed conceptual site layouts and renderings, and established a phased development strategy supporting future project expansion and reliable power delivery.